Kategori Digilib
Monthly Consultant Report Alor and Ende/Accompanying Measures May 2010 ProAir
Indonesian-German Development Cooperation Rural Water Supply and Sanitation Project Nusa Tenggara Timur (Pro Air), June 2010
Th. 2010
monthly report, ProAir, May 2010
Perpustakaan AMPL, e-book
920 kali
This progress report covers the period of May 2010. Reporting is done on the following issues:
1. Main Activities and Planned Activities
2. Problems, Constraints and Resolution Strategies
3. Project Progress according to Project Results
4. Project Management, Personnel, Logistics.
ANNEX
Alor – Actual and Planned Activities
Alor –Implementation Schedule – Material Supply and Construction Works
Alor – Cost Summary
Alor – Spring Yields in l/s
Ende – Actual and Planned Activities
Ende – Implementation Schedule – Material Supply and Construction Works
Ende – Cost Summary
Ende – Spring Yields (l/s) in Maukaro Sub-District
Ende – Spring Yields (l/s) in Detukeli Sub-District